Export rates from September 2019 - September 2021
V2G Customer Type | Quoted Export Rate |
---|---|
Without Domestic Solar PV | 30p/kWh bill credit |
With Domestic Solar PV | 26p/kWh bill credit |
Efficiency uplift factor: 1.12 (assumes 89% round trip efficiency for the V2G charger).
V2G Customer Type | Paid Export Rate |
---|---|
Without Domestic Solar PV | 33.6p/kWh bill credit |
With Domestic Solar PV | 29.1p/kWh bill credit |
Export rates from October 2021 - June 2022
V2G Customer Type | Quoted Export Rate |
---|---|
Without Domestic Solar PV | 35p/kWh bill credit |
With Domestic Solar PV | 31p/kWh bill credit |
Efficiency uplift factor: 1.12 (assumes 89% round trip efficiency for the V2G charger).
V2G Customer Type | Paid Export Rate |
---|---|
Without Domestic Solar PV | 39.2p/kWh bill credit |
With Domestic Solar PV | 34.7p/kWh bill credit |
Export rates from July 2022 - March 2023
V2G Customer Type | Quoted Export Rate |
---|---|
Without Domestic Solar PV | Import + 13.4p/kWh bill credit |
With Domestic Solar PV | Import + 9.9p/kWh bill credit |
Efficiency uplift factor: 1.12 (assumes 89% round trip efficiency for the V2G charger).
V2G Customer Type | Paid Export Rate |
---|---|
Without Domestic Solar PV | Import + 15p/kWh bill credit |
With Domestic Solar PV | Import + 11p/kWh bill credit |